EV Chargers
Installation of EV Chargers (Commercial projects)
- 1. Site preparation & SOP
- 2. Fabrication, supply & install of new EVDB
- 3. Complete wiring works
- 4. Upgrading of main breaker (if required)
- 5. Emergency stop button
- 6. Calibration (if required)
- 7. Fire fighting equipment
- 8. Cement plinth
- 9. Mobilisation of charger(s) to site w lorry crane
- 10. Testing & commissioning
- 11. ST Documentation (Borang G & H)
- 12. Application & submission of ST Licence
- 13. PBT application
- 14. Bomba application
Installation of EV Chargers (Residential)
- 1. PVC or metal EVDB
- 2. 6mm² or 10mm² cable option
- 3. PVC pipe, casing or metal trunking
- 4. Isolator
- 5. MCB & RCCB
- 6. Testing & commissioning
- 7. Cut ceiling, hack hole and make good
- 8. Single phase & three phase